20 NHBRC Test Questions, with Answers and Explanations
These free practice questions are also available in the app, covering foundations and flooring. Each one
shows the four options, which is correct, why it is correct, and the clause, table or figure in the
standard that settles it. Nothing here is behind a download.
Checked 6 September 2026Foundations 14 · Flooring 6
Foundations
SANS 10400-H
Question 1
Who is the most competent person that should design the Geotechnical solution
AA Civil Engineer
BA Geotechnical Engineer, correct answerAnswer
CAn NHBRC Inspector
DNone of the above
Answer B: A Geotechnical Engineer. The standard reserves this work for a “competent person (geotechnical)”. Definition 3.10 asks for more than registration: suitable experience in geotechnical site investigations or foundation design. A general civil engineer does not automatically hold that experience, and an inspector checks work rather than designs it.
SANS10400-H Foundation: Page 5
Question 2
A dolomite feature that manifests as a hole in the ground is referred to as
AA sink hole, correct answerAnswer
BA mine
CA shaft
DAll of the above
Answer A: A sink hole. Definition 3.40 states that a sinkhole is a feature that occurs suddenly and manifests itself as a hole in the ground. The suddenness is the point: subsidence is the slower settlement that happens when sinkhole formation stops early or the overburden consolidates.
SANS10400-H Foundation: Page 9, Par 3.40
Question 3
What is the purpose of a geotechnical site investigation in the home building sector
ATo create more work for engineering geologists & geotechnical engineers
BTo document the parameters upon which the design of the foundation is to be based, correct answerAnswer
CHelp council of geoscience and NHBRC collect information
DIncrease the cost of the house
Answer B: To document the parameters upon which the design of the foundation is to be based. Clause 4.2.1 sets out the purpose of the investigation: to document and form an opinion on the parameters the foundation design will rest on, and to classify the site against table 1. It is the input to a design decision, not paperwork produced for its own sake.
SANS10400-H Foundation: Page 11, par 4.2.1
Question 4
Which one of the following soils expands considerably when water is added
AClay soil site classification 'H", correct answerAnswer
BRocks site classification "R"
CDolomitic areas site classification "P"
DNone of the above
Answer A: Clay soil site classification 'H". Table 1 groups fine-grained soils of moderate to very high plasticity (clays, silty clays, clayey silts and sandy clays) as expansive soils, designated H. They take up water and swell, then shrink as they dry, and that cycle is what cracks the masonry above them. Rock is class R and dolomite land falls under P.
SANS10400-H Foundation: Page 11, Table 1
Question 5
In terms of the NHBRC soil class classification, what is a "P" soil type classification
ARock
BClays
CSand
DContaminated soil, fill & marshes, correct answerAnswer
Answer D: Contaminated soil, fill & marshes. Class P is table 1’s designation for ground whose behaviour the usual descriptors cannot predict: contaminated soils, controlled and uncontrolled fill, dolomite land, landslip, landfill, marshy areas, mine waste and mining subsidence. Rock, clay and sand each have classes of their own.
SANS10400-H Foundation: Page 11, Table 1
Question 6
What types of soil are good for construction
ARock soil, correct answerAnswer
BPeat
CClay
DSand and gravel
Answer A: Rock soil. Table 1 ranks founding materials by how much they move. Rock is the only entry listed as stable with negligible movement, site class R. Clays are expansive, and sands and gravels are compressible or potentially collapsible, so every other option brings movement the design has to absorb.
SANS10400-H Foundation: Page 11, Table 1
Question 7
What is the minimum founding depth for slab on the ground foundation type
A500mm
B1500mm
C300mm, correct answerAnswer
D400mm
Answer C: 300mm. Figures 3 and 4 dimension the slab-on-the-ground option at 300 mm minimum, against 400 mm for a strip footing in the same drawings. A slab spreads load across its whole area instead of concentrating it in a trench, so it does not have to reach as deep.
SANS10400-H Foundation: Page 16, Fig.a
Question 8
Except founded on rock, the minimum founding depth for a strip footing below natural ground level shall not be less than
A150mm
B400mm, correct answerAnswer
C600mm
D300mm
Answer B: 400mm. Figure 5 marks the strip footing “400 min.”, with rock called out as the exception. Rock is excepted because it is already a stable founding material; everything else has to get below the zone where seasonal moisture moves the soil.
SANS10400-H Foundation: Page 16 Fig.b or Page 17 Table 3
Question 9
The minimum width of a strip foundation for a single storey building with a tiled or sheeted roof in stable soil conditions for an external & internal wall shall be .... respectively
A200mm for the external wall & 400mm for the internal wall
B400mm for the external wall & 200mm for the internal wall
C500mm for the external wall & 400mm for the internal wall, correct answerAnswer
D400mm for the external wall & 500mm for the internal wall
Answer C: 500mm for the external wall & 400mm for the internal wall. Table 3 splits the width by wall and by roof. For soil under a tiled or sheeted roof it asks 500 mm on the external wall and 400 mm internally. The external wall takes the roof load down one side, so it needs the wider spread. On rock both drop to 400 mm.
SANS10400-H Foundation: Page 17, Table 3
Question 10
What is the minimum slab thickness of a strip foundation
A150mm
B200mm, correct answerAnswer
C400mm
D600mm
Answer B: 200mm. Clause 4.3.2.2.1(c) sets the thickness at not less than 200 mm, with one exception: bearing straight onto solid rock, where it need only be thick enough to give a level surface. Width comes from table 3. Thickness is specified separately.
SANS10400-H Foundation: Page 17, Par 4.3.2.2.1ac
Question 11
What is the minimum width of a non-continuous strip foundation to an internal masonry non load bearing wall or a timber framed wall supporting a roof with class A or class Cl
A100mm
B400mm, correct answerAnswer
C600mm
D700mm
Answer B: 400mm. Table 3’s note allows 400 mm for internal walls carrying no bearing from a reinforced concrete roof, the same width the table already gives internal walls under a tiled or sheeted roof. The wider 600 mm and 750 mm figures apply only once a concrete roof bears on the wall.
SANS10400-H Foundation: Page 17, Table 3
Question 12
What is the minimum internal & external width of a strip foundation C, H, R and S soil classification sites on reinforced concrete roofs
A400mm & 500mm
B750mm & 600mm, correct answerAnswer
C800mm & 1000mm
D1000mm & 1200mm
Answer B: 750mm & 600mm. Table 3’s reinforced concrete roof columns read 750 mm internal and 600 mm external on soil. The internal figure being the larger one catches people out: an internal wall under a concrete roof can pick up load from both sides, while an external wall picks it up from one.
SANS10400-H Foundation: Page 17, Table 3
Question 13
What does the dolomite condition mean
AA white mineral often tinted by impurities, found in sedimentary rocks and veins. It is used in the manufacture of cement and as a building stone (marble)
BAn acidic type of soil
CA rock formed from volcanic conditions
DSink hole, correct answerAnswer
Answer D: Sink hole. What makes dolomite land hazardous in this standard is not the mineral but the sinkhole. Definition 3.40 describes a feature that occurs suddenly and manifests as a hole in the ground. Annex A.7.3 is built around keeping a building standing, and its occupants able to escape, if one opens beneath it.
SANS10400-H Foundation: Page 31, Par A.7.3.1
Question 14
What type of foundation is needed in a dolomite classified area
AA strip foundation
BA raft, mat or slab on the ground foundation, correct answerAnswer
CA dolomite foundation
DA pad foundation
Answer B: A raft, mat or slab on the ground foundation. Clause A.7.3.1(d) requires a soil mattress or a reinforced concrete foundation on D3 dolomite sites, and A.7.3.4 sets what it has to survive: a loss of support 2 m or 5 m across, anywhere under the building. A strip footing cannot bridge a void of that size; a raft, mattress or slab can.
SANS10400-H Foundation: Page 33, Par A.7.3.4
Flooring
SANS 10400-J
Question 15
What is the minimum required width of a wooden floor
A50mm, correct answerAnswer
B140mm
C600mm
D900mm
Answer A: 50mm. Definition 3.7 fixes a flooring board’s face side width between 50 mm and 140 mm, so 50 mm is the floor and 140 mm the ceiling. Both limits come from that one definition, which is why the pair of questions has the same source.
SANS10400-J Flooring: Page 5, Par 3.7
Question 16
What is the maximum required width of a wooden floor
A50mm
B140mm, correct answerAnswer
C600mm
D900mm
Answer B: 140mm. Definition 3.7 caps a flooring board’s face side width at 140 mm, with 50 mm as the lower bound. Capping the width matters because timber moves most across the grain: the wider the board, the more it cups and shrinks in service.
SANS10400-J Flooring: Page 5, Par 3.7
Question 17
What is the minimum height above ground level for timber floor joists
A150mm
B250mm
C350mm
D450mm, correct answerAnswer
Answer D: 450mm. Clause 4.3.3 requires at least 450 mm between the under-surface of the ground floor joists and the ground below. That gap is what lets the subfloor ventilate and be inspected; the same clause calls for access and for all debris to be cleared from the void.
SANS10400-J Flooring: Page 10, Par 4.3.3
Question 18
Compaction by hand shall be in layers not exceeding
A100 mm, correct answerAnswer
B150 mm
C250 mm
D350 mm
Answer A: 100 mm. Clause 4.4.6 sets two layer thicknesses and the tool decides which applies: 100 mm for hand compaction, 150 mm by mechanical means. Hand compaction gets the thinner layer because it drives less energy into the fill.
SANS10400-J Flooring: Page 11, par 4.4.6
Question 19
Compaction by mechanical means shall be in layers not exceeding
A100 mm
B150 mm, correct answerAnswer
C250 mm
D350 mm
Answer B: 150 mm. Clause 4.4.6 allows 150 mm uncompacted layers where compaction is mechanical, against 100 mm by hand, and each layer must be well compacted before more fill goes on. The limit is about getting compaction right through the depth, not about how fast the fill is placed.
SANS10400-J Flooring: Page 11, par 4.4.6
Question 20
The maximum height of fill beneath floor slab and slab on the ground foundation measured at the lowest point shall not exceed... mm unless certified by a competent person
A200 mm
B400 mm, correct answerAnswer
C300 mm
D500 mm
Answer B: 400 mm. Clause 4.4.7 hands the job to a competent person (civil engineering) once fill beneath a floor exceeds 400 mm at any point. Deep fill settles under its own weight as well as the building’s, so past that depth it stops being a standard detail and becomes a design.
SANS10400-J Flooring: Page 11, Par 4.4.7
Answer Key
Use this to check your answers after practising or printing the page.
Hidden while you test yourself. Turn off “Hide the answers” at the top of the page to see it.
Full Access opens all 277 questions, timed tests marked against the
same 80% pass mark the app uses, drills built from the areas costing
you marks, and the 15 reference documents. One payment of
R340, and it never renews.
Exported from our question bank and reviewed against the standard each one cites; last
checked 6 September 2026. They are practice questions written from the published
standards, not the assessment’s own questions. Our
editorial policy sets out what that check is, and what fails it.